[NEMO-devel] To control RE limit
Ben Elliston
bje at air.net.au
Thu Aug 17 17:00:38 AEST 2017
Hi Yusak
> Instead of controlling fossil limit using --fossil-limit, can we
> also directly control renewable energy penetration limit, where we
> can arrange RE limit up to certain percentage, using certain
> command?
The simulated generators are either classified as fossil or renewable
(there is no nuclear generator model as yet), so you can ensure a
minimum level of RE using a fossil limit of 1-x (ie. a fossil limit of
20% is a minimum of 80% RE).
If you want to impose a maximum level of RE, you'll need to write a
new penalty function in evolve.py and add it to the penaltyfns list
also in evolve.py.
Cheers, Ben